UPDATE: STOP-AND-GO BETWEEN STANFORD AND HERMANUS 03.11.2021

UPDATE: STOP-AND-GO BETWEEN STANFORD AND HERMANUS 03.11.2021

Overstrand Municipality

UPDATE: STOP-AND-GO BETWEEN STANFORD AND HERMANUS 03.11.2021

We received the following feedback of the R43 between Stanford and Hermanus from EFG Engineer, Brian Domingo:

The section over the Vogelgat culvert will be open within the next week. It will still be single lane traffic, but diverted onto the new road over the culvert.

In order to remove the stop/go, the surfacing work needs to be completed.

Domingo said they are aiming for December 2021, "but in all likelihood it will only be towards end January 2022 after the builder's break".

UPDATE: STOP-AND-GO BETWEEN STANFORD AND HERMANUS 03.11.2021

Overstrand Municipality

In the background, though, a top performer - Overstrand Municipality - labours relentlessly to ensure this treasure trove’s clockwork ticks over smoothly. Providing municipal services to an area exceeding 1708 km2 with a population well in excess of the estimated 74500 souls is no easy feat, as th...

View Profile

What is Xplorio?

Xplorio is your local connection allowing you to find anything and everything about a town.

WATCH THE VIDEO: Welcome to Hermanus
Read More

Recent Posts

Seal Rabies Cases Confirmed in Overstrand

Seal Rabies Cases Confirmed in Overstrand

Rabies detected in the Cape Fur Seal population has spread from beaches.

ELECTRICITY TARIFFS - Unit Scale

ELECTRICITY TARIFFS - Unit Scale

Please take note of the new unit scale for pre-paid electricity tariffs to be implemented as from 1 July 2024.

SANRAL Training for Local Contractors

SANRAL Training for Local Contractors

SANRAL training to assist local contractors to access opportunities within construction industry.

NHBRC Technical Training for Emerging Contractors

NHBRC Technical Training for Emerging Contrac...

If you are in the building industry or any construction-related field, this National Home Builders Registration Council (NHBRC) training is for you.

11 New Generators Installed to Safeguard Water and Waste-Water

11 New Generators Installed to Safeguard Wate...

The last of the back-up generators was installed at the Baardskeerdersbos WTW at the end of February 2024.

Home Affairs Dates for March 2024

Home Affairs Dates for March 2024

The Department of Home Affairs (DHA) confirmed that their Mobile Unit's scanner machine is still out of order.