Kleinmond Modern Home Project
Exciting news from our Kleinmond project! Since May 2024, our team has been hard at work, overcoming typical construction challenges with impressive efficiency.
• May 2024: Site clearance and marking began.
• May 10: Mattress for the raft foundation completed.
• Days 12-15: Foundation preparation, steel beams, and slab boxes installed.
• Day 15: First walls erected, marking a major milestone.
• Days 31: Roof beams, electrical fittings, and fencing completed.
As of August 8th, the structure is ready for its first coat of plaster.
This project is a testament to how a well-coordinated team can bring a high-quality home to life in record time. Stay tuned for more updates as this modern dwelling in Kleinmond continues to take shape.