UPDATE: STOP-AND-GO BETWEEN STANFORD AND HERMANUS 03.11.2021
We received the following feedback of the R43 between Stanford and Hermanus from EFG Engineer, Brian Domingo:
The section over the Vogelgat culvert will be open within the next week. It will still be single lane traffic, but diverted onto the new road over the culvert.
In order to remove the stop/go, the surfacing work needs to be completed.
Domingo said they are aiming for December 2021, "but in all likelihood it will only be towards end January 2022 after the builder's break".